R27169 Depreciation - Check Start Date

Code R27169
Entity Finance.Assets.Depreciations Entity
Name CheckStartDate
Attribute StartDate
Layer Back-End
Events Planned +
Modify NO
Action Validate that:

StartDate == IsFirstDayOfAMonth
Description On any document status change, the system checks that the StartDate is a first day of a month. For example "2020/12/01" - this is a correct start date. "2020/12/02" is an incorrect StartDate
Message "The start date or the end date in depreciation '{0}' is invalid. The start date must be first day of month and the end date must be last day of month.", [DocumentText]





Message also used in:

R27171 Depreciation - Check End Date
Introduced In Version 2017
Revocable NO

* For more information about the Business Rules Documentation Template and a short explanation of each column, see topic System Business Rules.